Lagos State Governor Babajide Sanwo-Olu has said the Opebi-Odoiya Alaro Bridge will be available to motorists before the holiday season, following a delay caused by work to install a major steel artwork at the site.
Sanwo-Olu gave the update in a post on X after visiting the project to review construction progress and determine why the planned opening had slipped. He had previously said the bridge was expected to begin carrying traffic by the end of September, based on the delivery schedule presented by the contractors.
The governor said the delay relates to the installation of a 25-metre steel monument intended to preserve the memory of Cane Village, the former settlement in the area that was widely known for its cane trading market.
Designed as four hands weaving cane, the installation is meant to reflect the community’s cultural legacy while providing a recognisable feature along the road corridor. Three of its four steel sections have already been assembled and fixed in place, while installation work continues on the remaining section.
“The monument is now 80% complete and we need just a few more days to finish the work,” Sanwo-Olu said.
He said the bridge could not be opened on the original timetable because the monument must be securely fitted before vehicles are allowed onto the route. “Safety remains our priority so we cannot open the road until every section is securely in place,” he stated.
Apologising for the disruption to road users, the governor asked motorists to remain patient and said the bridge would be commissioned before the holidays, easing travel along the corridor.